Please note that the majority of these conditions can be allowed for in our price if required

  1. Where possible we will weld all steel to steel connections.
  2. It is the main contractors responsibility to provide protection to existing structures near any hot-works being carried out. This is because we do not carry the gear to protect windows, roofs etc.
  3. All primer painted material must be clad or top-coated within one month of application to avoid damage to paint system.
  4. All zinc-metal sprayed material must be clad in or top coated with an approved paint system within 3 months of application to avoid damage to the paint system.
  5. All propping and scaffolding is to be provided by the main contractor.
  6. All dry-packing is to be provided by the main contractor.
  7. We will drill all holes through all steel unless it is noted on the drawings that no holes are required.
  8. We will supply all steel to concrete bolts and steel to steel bolts (galvanised only).
  9. All steel to timber bolts and holes through timber are the responsibility of the main contractor.
  10. A full set of council stamped engineering and architectural drawings must be on site at all times and our staff must have unrestricted access to them.
  11. There must be sufficient power on site to run a caddy welder (12amp fuse or better). If a welder generator is required, all charges will be forwarded to the main contractor.
  12. There is no allowance in our price for core drilling of holes through concrete if reinforcing steel is hit while we are drilling steel to concrete connections. If this occurs we will offer to provide a concrete cutting service. The minimum charge for this is $215.00 + GST.
  13. There must be a representative of the Main Contractor on site at the commencement of the project and during installation of steelwork.